PLI Scheme Details
- The scheme provides financial incentive (cash subsidy) for setting up manufacturing facility for advanced battery pack and advance chemistry cells (“ACC”);
- A cumulative ACC manufacturing capacity of 50 GWh for ACC shall be allocated to selected investors based on techno financial bid (Quality and cost based selection process);
- Additional incentive for manufacturing capacity of 5 GWh for niche ACC manufacturing;
- Total incentive to be capped at 20 GWh for a single beneficiary;
- Incentive not available for conventional battery pack segment as assembly already happening in India;
- Subsidy to be disbursed once value add and sale of ACC begins;
- Manufacturing to commence in 2 years time and the incentive will be given over 5 year after manufacturing commences;
- Expected cumulative capital outlay under the scheme is INR 45,000 crores
- The scheme will also provide for a detailed testing framework for verifying the performance standards.
- The incentive would be in the form of Cash Subsidy that shall be disbursed based on overall value-addition on per Kilo Watt hour (“KWh”) basis.
- The applicant shall submit its bid for the base-subsidy (benchmark subsidy = INR 2000/KWh), which would be available on pro-rata basis upto 100% domestic value capture and for manufacturing of ACCs
Technical Specifications
ACCs | Energy Density (Wh/Kg) ~ (Specific Density) | |||||
≥ 50 | ≥ 125 | ≥ 200 | ≥ 275 | ≥ 350 | ||
Cycle Life | <1000 |
N.A |
N.A |
N.A | N.A | ACC (1/5) |
≥ 1000 | ACC (2/4) | ACC (2/5) | ||||
≥ 2000 | ACC (3/3) | ACC (3/4) | ACC (3/5) | |||
≥ 4000 | ACC (4/2) | ACC (4/3) | ACC (4/4) | ACC (4/5) | ||
≥ 10000 | ACC (5/1) | ACC (5/2) | ACC (5/3) | ACC (5/4) | ACC (5/5) |
PLI Scheme – ACC Battery – Gazette Notification